HomeMy WebLinkAboutVIII-04 Approve Change Order No. 4 for Hastings Public Works Storage Building City Council Memorandum
To: Mayor Fasbender & City Council Members
From: Ryan Stempski – Public Works Director/City Engineer
Date: November 30, 2022
Item: Approve Change Order No. 4 for the Hastings Public Works Storage Building
COUNCIL ACTION REQUESTED
Council is requested to approve attached Change Order No. 4 for the Hastings Public Works Storage Building
Project.
BACKGROUND INFORMATION
Change Order No. 4 covers the cost of additional electrical wiring necessary for both a horn strobe fire alarm and
an air compressor for the fire suppression system required by the Hastings Fire Department that was not
included on the original electrical plans.
FINANCIAL IMPACT
The value of the work contemplated by Change Order No. 4 is an increase of $1,251.90.
Below is a table summarizing the change orders to date.
2022-3 Hastings Public Works Storage Building
Change
Order Date Item
Estimated
Value
1 8/22/2022 Change Order No. 1 $56,237.27
2 9/19/2022 Change Order No. 2 $10,410.03
3 10/6/2022 Change Order No. 3 $1,439.15
4 11/8/2022 Change Order No. 4 $1,251.90
Net Total Increase/(Decrease) to date $69,338.35
Original Contract Value $1,310,400.00
Revised Contract Value $1,379,738.35
Change Orders as Percentage of Original Contract Value to date 5.3%
STAFF RECOMMENDATION
Staff recommends approval of attached Change Order No. 4.