To: Mayor Fasbender & City Council Members
From: Ryan Stempski – Public Works Director/City Engineer
Date: February 16, 2022
Item: Contract Award for W 4th Street Water Tower Reconditioning
COUNCIL ACTION REQUESTED
Council is requested to adopt the attached resolution to award a contract for the W 4th Street Water Tower
Reconditioning.
BACKGROUND INFORMATION
The City received five bids for this project on February 9th. A summary of the bids is listed below.
Bidder Total Base Bid Alternate Bid
G&L Tank Sandblasting and Coatings LLC – Shelbyville, TN $722,500.00 $3,500.00
Osseo Construction Co. LLC – Osseo, WI $876,000.00 $12,000.00
Classic Protective Coatings, Inc. – Menomonie, WI $971,958.00 $6,500.00
JR Stelzer Co. – Lincoln, NE $1,107,750.00 $8,000.00
TMI Coatings, Inc. – St. Paul, MN $1,155,000.00 $9,000.00
The low bid from G&L Tank Sandblasting and Coatings LLC came in 52% under the engineer’s estimate, which
was $1,400,000. This bid positions the project to come in within the 2022 budget. KLM Engineering (City’s
Water Tower Consultant) stated the bid amounts overall were significantly lower than originally predicted due
to the fact that the project schedule is occurring at a period when bidders were aggressively looking to fill their
2022 schedules. The City’s prevailing wage policy also did not apply to this unique project; therefore, labor and
overhead were left to the competitive market.
STAFF RECOMMENDATION
Staff is recommending that the City Council move forward in adopting the attached resolution awarding the
contract to G&L Tank Sandblasting and Coatings LLC, in the total amount of $726,000.00 (which includes the
alternate bid for adding “Home of the Raiders” facing the high school). Please refer to the attached award
recommendation letter from KLM Engineering.
ATTACHMENTS
Resolution Receiving Bids and Awarding Contract
Award Recommendation Letter from KLM Engineering
IX-03
CITY OF HASTINGS
DAKOTA COUNTY, MINNESOTA
RESOLUTION NO.
RESOLUTION RECEIVING BIDS AND AWARDING CONTRACT FOR W 4TH STREET WATER TOWER
RECONDITIONING
WHEREAS, pursuant to an advertisement for bids for the W 4th Street Water Tower Reconditioning project, bids
were opened on February 9, 2022 and tabulated according to law, and the following bids were received:
Bidder Total Base Bid Alternate Bid
G&L Tank Sandblasting and Coatings LLC – Shelbyville, TN $722,500.00 $3,500.00
Osseo Construction Co. LLC – Osseo, WI $876,000.00 $12,000.00
Classic Protective Coatings, Inc. – Menomonie, WI $971,958.00 $6,500.00
JR Stelzer Co. – Lincoln, NE $1,107,750.00 $8,000.00
TMI Coatings, Inc. – St. Paul, MN $1,155,000.00 $9,000.00
and
WHEREAS, it is recommended that the contract be awarded with the Alternate Bid, which includes the “Home of
the Raiders” lettering requested by the School District, and
WHEREAS, it appears that G&L Tank Sandblasting and Coatings LLC is the lowest responsible bidder.
NOW, THEREFORE BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF HASTINGS AS FOLLOWS:
1. The Mayor and Clerk are hereby authorized and directed to enter into a contract with G&L Tank
Sandblasting and Coatings LLC.
2. The total amount of the contract is hereby declared to be $726,000.00.
ADOPTED BY THE CITY COUNCIL OF HASTINGS, MINNESOTA, THIS 22nd DAY OF FEBRUARY, 2022.
Ayes:
Nays:
Mary D. Fasbender, Mayor
ATTEST:
Kelly Murtaugh, City Clerk
SEAL
IX-03
Corporate Office
1976 Wooddale Drive, Suite 4
Woodbury, MN 55125
“Protecting America’s Water, One Tank at a Time.”
February 15, 2022
Ryan Stempski, P.E. by Email
Public Works Director/City Engineer
City of Hastings
1225 Progress Drive
Hastings, MN 55033
RE: Bid evaluation for Cleaning, Repairing, & Painting of the 750,000-Gallon Elevated
Reservoir (4th Street Tower) for the City of Hastings, MN. City Project No. 2022-2, KLM
Project No. 1574-21.
Mr. Stempski,
The project bid opening was held on Wednesday, February 9, 2022, at 2:00 PM CST. Bids
were opened publicly through QuestCDN’s online bidding platform. Bids received were as
follows:
Bidders Base Bid School Logo Add.
Alternate Bid
G&L Tank Sandblasting and
Coatings LLC
$722,500.00 $3,500.00
Osseo Construction Co. LLC $876,000.00 $12,000.00
Classic Protective Coatings, Inc. $971,958.00 $6,500.00
J.R. Stelzer Co. $1,107,750.00 $8,000.00
TMI Coatings, Inc. $1,155,000.00 $9,000.00
In review of documentation provided by each of the bidders, all bidders meet the qualifications
of the Specifications and are considered responsible bidders eligible for award of this project.
The low bidder, G&L Tank Sandblasting and Coatings LLC, does not have a work history with
KLM Engineering. As a result, several of G&L’s provided municipal and consultant references
for recent similar projects in Kentucky, Oklahoma, Missouri, Tennessee, and Minnesota, along
with some manufacturer representatives known to KLM, were contacted. Responses were all
positive, noting they were happy with the work performed, sites were kept clean, and work was
done on time or ahead of schedule. A couple of the municipalities have already gone forward
with awarding additional work to G&L.
In addition to contacting references, KLM had a lengthy video conference call with G&L to
discuss their company history and work experience, KLM’s expectations, general work
performance measures, and project specific details. G&L also confirmed their intent to honor
their Bid Proposal amounts. Bid amounts overall were significantly lower than originally
predicted. The consensus of the bidders contacted was that the project schedule is occurring at
a period most were still aggressively looking to fill in their predominantly busy 2022 season
schedules.
IX-03
Corporate Office
1976 Wooddale Drive, Suite 4
Woodbury, MN 55125
“Protecting America’s Water, One Tank at a Time.”
Given the information received, KLM recommends awarding the contract to the lowest qualified
bidder, G&L Tank Sandblasting and Coatings LLC, for the Base Bid amount of $722,500.00.
KLM also recommends including award of the School Logo Add. Alternate Bid amount of
$3,500.00, in anticipation the School District will pursue application of their logo.
Please feel free to contact me with any questions.
Sincerely,
KLM Engineering Inc.
Rodney Ellis
VP/COO