HomeMy WebLinkAbout04/13/92Hastings Planning Commission
Meeting of April 13, 1992
The regular meeting of the Hastings Planning Commission was called to
order by Commissioner Reinardy at 7:00 p.m.
Commissioners Present: Anderson, Bateman, Bolesworth, Mesaros, Reinardy
and Zender
Commissioners Absent: Featherstone
Staff Present:
Community Development Director Wozniak and City Planner
Czech
Commissioner Reinardy called for additions or
corrections to the minutes of the regular meeting
of March 9, 1992. There being no additions or
corrections to the minutes, the minutes were
approved.
MINUTES
Czech reviewed staffs April 7, 1992, memorandum to
the Planning Commission concerning a request by
the Dakota County HRA for approval of a site plan
for a senior housing project to be located on East
3rd Street between Ramsey and Tyler Streets.
DAKOTA COUNTY HRA
SENIOR HOUSING -
EAST 3RD STREET
The Planning Commission discussed with staff,
Kirk Velett of Arvid Elness Architects who represents
Dakota County HRA, Diane Nordquist of the Dakota County
HRA issues relating to the proposed senior housing
project including, but not limited to, proposed size
of the facility and rents.
Commissioner Mesaros moved, Commissioner Bolesworth
made a second, to approve the site plan subject to
the following conditions:
The proposed structure and accessory items
including, but not limited to, the parking lot
and landscaping shall be completed pursuant to
the approved site plan. Upon request for occupancy
of the building, all uncompleted items contained
within the site plan shall be addressed pursuant
to the escrow requirements contained within the
site plan review provisions of the city's zoning
ordinance (Section 10.24).
B. The applicant/owner shall provide off site parking
which satisfies City Code requirements.
C. The applicant/owner shall satisfy all Uniform
Building and Fire Codes.
Upon vote taken, Ayes, 7; Nays, 0.
Bill Sylvander who was present at the meeting indicated
that he was representing his father (an adjacent property
owner) and inquired about underground parking.
Czech reviewed staff's March 31, 1992, memorandum to
the Planning Commission concerning a request by
Guetschoff Theaters, Inc. for approval of a site
plan to convert the existing Top Do It Center into
a movie theater located at 1325 South Frontage Road.
The Planning Commission discussed with staff and
Bob Guetschoff the applicant issues relating to the
proposed theater including, but not limited to, the
number of screens and location of other theaters
owned by Guetschoff Theaters, Inc.
SITE PLAN-MOVIE
THEATER -
GUETSCHOFF
THEATERS, INC.
1325 SOUTH
FRONTAGE ROAD
Commissioner Anderson moved, Commissioner Mesaros
made a second, to approve the site plan subject to
the following conditions:
The proposed structure and accessory items including,
but not limited to, the parking lot, front facade
and signage be completed pursuant to the approved
site plan. Upon request for occupancy of the building,
all uncompleted items contained within the site plan
shall be addressed pursuant to the escrow requirements
contained within the site plan review provisions of
the city zoning ordinance (Section 10.24).
B. That the applicant/owner shall satisfy all Uniform
Building and Fire Codes.
Upon vote taken, Ayes, 6; Nays, 1 (Bateman).
Czech reviewed staff's April 7, 1992, memorandum
to the Planning Commission concerning a request
by Greg Jablonske of Advanced Homes of Hastings
for approval of a final plat and revised grading
plan for Riverwood 5th Addition.
FINAL PLAT/
REVISED GRADING
PLAN-RIVERWOOD
5TH ADDITION -
ADVANCED HOMES
The Planning Commission discussed with staff issues
relating to the proposed final plat and revised
grading plan including, but not limited to, the
number of cul de sacs and future additions.
Commissioner Zender moved, Commissioner Mesaros made
a second, to approve the final plat and revised
grading plan subject to the following conditions:
That any structures located on Lots 1, 2
and/or 3 be located at least 50 feet from the
Northern Natural Gas Company Pipeline easement.
If the developer is unable to situate a structure
on Lot 2 so as to comply with the 50 foot setback
requirement, the developer shall replat that lot
so as to comply with the 50 foot setback requirement.
Prior to any building permits being issued,
the developer shall provide a certified survey
that the entire site has been graded pursuant to
the revised grading plan dated April 2, 1992.
Furthermore, prior to any building permits being
issued for that area proposed as Riverwood 6th
Addition (Outlot A), the developer shall provide
a certified survey that the entire site as indicated
on the 3-19/4-16-91 preliminary plat has been graded
pursuant to the 3-19/4-16-91 preliminary plat.
Compliance with all conditions of the preliminary
plat for Riverwood 5th & 6th Additions as approved
by the City Council on May 20, 1991.
That the developer enter into a Development Agreement
with the City of Hastings incorporating conditions
number 1, 2 and 3 listed above.
Upon vote taken, Ayes, 7; Nays, 0.
Czech reviewed City Council action pertaining to
Planning items from the Councils' April 6, 1992,
meeting.
UPDATES/OTHER
BUSINESS
Czech inquired as to whether the Planning Commission
would be interested in further discussing the
Comprehensive Plan Update after adjourning the regular
meeting. The Planning Commission indicated that they
would like to meet.
There being no further business, Commissioner Zender
moved, Commissioner Mesaros made 'a second, to adjourn
the meeting at 7:35 p.m.