HomeMy WebLinkAbout20120820 - VI-04 Council Action Requested: The Council is requested to formally approve Change Order #1 for the Vermillion Trail & Underpass Connection project. Background Information: The contractor requested permission to place the bituminous pavement for the trail in one layer rather than two, citing that the projects physical space constraints, particularly through the wooded section of the trail, would lead to a higher probability that end-product quality and workmanship would be negatively impacted. City staff negotiated a slight discount of the bituminous mixture price to achieve savings in exchange for making this exception to the specifications and plans, as it would reduce the amount of time and mobilizations that the contractor would have to invest to complete the project. Financial Impact: Thus far, the estimated total impact of change orders for this contract project to an decrease in construction expenses of $2,375.00, or about 0.49% of the original contract value. Vermillion Trail & Underpass Connection Change Order Summary Change Order Date Items Estimated Value 1 8/2/2012 Bituminous Paving in Single Lift $(2,374.05) Net Total Increase/Decrease to date $(2,374.05) Original Contract Value $489,205.15 Change Orders as Percentage of Contract Value to date -0.49% Attachments: Change Order #1 has been attached for reference. To: Honorable Mayor & City Council From: Nick Egger – City Engineer Date: August 13, 2012 Re: Change Order #1 – Vermillion Trail & Underpass Connection 1 City of Hastings Engineering Department Change Order #1 City Project No.: 2012-2 Contractor: Blackstone Contractors, LLC Address: 7775 Corcoran Trail East Corcoran, MN 55340 Contract Name: Vermillion Trail & Underpass Connection The City of Hastings and Blackstone Contractors, LLC hereby agree to this change order to provide compensation for installing the trail segments throughout the project in a single 3” lift. Per the Contractor’s request, the City has agreed to allow for installation of the trail segments throughout the project to be done in a single 3” lift instead of 2 1.5” lifts. The Contractor requested this change to eliminate truck damage to the base course. Because mobilization costs associated with this change decrease, the Contractor agrees to a $3.57 per ton discount on that portion of trail installed in a single lift. A new item in the account records will be created to compensate for this work. It will be described as: CHANGE ORDER #1 – BIT WEAR COURSE MIX SPWEA240B (TRAIL) 3” LIFT. The 2 2 existing items for trail paving non-wear and wear courses will be deleted. Please refer to the following table for further information: ITEM NO. DESCRIPTION UNIT OLD QUANTITY NEW QUANTITY REVISED UNIT PRICE TOTAL CHANGE 58 (NEW) CHANGE ORDER #1 – BIT WEAR COURSE MIX SPWEA240B (TRAIL) 3” LIFT TON 0 1190 $78.33 $93,212.70 21 (DELETE) BITUMINOUS WEARING COURSE MIX SPWEA240B (TRAIL) TON 595 0 $81.90 ($48,730.50) 23 (DELETE) BITUMINOUS NON WEAR COURSE MIX SPNWB230B (TRAIL) TON 595 0 $78.75 ($46,856.25) ESTIMATED CHANGE IN TOTAL CONTRACT AMOUNT ($2,374.05) Approved By: ____________________________ Accepted By: ______________________________ City Engineer Blackstone Contractors, LLC Authorized Representative Date: Date: ___________________ 8/2 /2012