HomeMy WebLinkAbout20100719 - VI-06MEMO
To: Honorable Mayor and City Council
From: Nick Egger — City Engineer
Date: July 14, 2010
Re: Change Order #5 for 2009 Industrial Park Area Improvements
Enclosed for Council approval is Change Order #5 for the 2009 Industrial Park Area Improvements
project. This change order provides compensation to the contractor for achieving the asphalt density
incentive threshold, as prescribed by MnDOT specifications.
State Aid projects are required to provide an asphalt density incentive or disincentive to the contractor
based on test results of core samples taken from the project. Three density tests were conducted. Test 1
of 3 resulted in a net incentive of $2,379.58. Test 2 of 3 resulted in a net incentive of $0.00. Test 3 of 3
resulted in a net disincentive of $1,442.63. A total net incentive of $936.95 was achieved.
Thus far, the estimated total impact of change orders on this project amount to an aggregate increase of
$2,644.34, or about 0.12% of the total contract value. At this time, approximately 99.9% of all
construction quantities have been completed for the contract, and the second to last payment to the
contractor is also included on the Agenda for Council approval.
2009 Industrial Park Improvements Change Order Summary
Change
Order
Date
Items
Value
1
9/16/2009
Lighting, Ravine Materials
- $6
2
11/9/2009
Storm Sewer, Lighting Components
$10
3
12/17/2009
Trail Paving, Traffic Markings
- $2
4
1/13/2010
Tree Stump Removal
$440.00
5
7/9/2010
Asphalt Density Incentive
$936.95
Net Total Increase
$2
Original Contract Value
$2
Change Orders as Percentage of Contract Value
0.12%
CITY OF HASTINGS
ENGINEERING DEPARTMENT
CHANGE ORDER #5
Contractor: Northwest Asphalt, Inc. City Project No.: 2009 -1
Address: 1.451 Stagecoach Road
Shakopee, MN 55379
Contract Name: Industrial Park Area Improvements
The City of Hastings and Northwest Asphalt, Inc. hereby agree to this change order to provide compensation for bituminous
density incentive/disincentive per State Aid requirements.
1. B iturninous Density Incentive,/Di
State Aid projects are required to provide a bituminous density incentive or disincentive to the contractor based on test
results of core samples taken from the project. Three. density tests were conducted consisting of 12 lots. Test 1 of 3
resulted in a net incentive of $2,379.58. Test 2 of 3 resulted in a net incentive of $0.00. Test 3 of 3 resulted in a net
disincentive of - $1,442.63. A total net incentive of $936.95 was achieved. Refer to the complete test results attached
for further information.
ITEM
TOTAL
NO.
DESCRIPTION
UNIT
QUANTITY
UNIT PRICE
CHANGE
NE4 W
BIT DENSITY
LS
1
$936.95
$936.95
INCENTIVEIDISINCENTIVE
ESTIMATED CHANGE IN TOTAL CONTRACT AMOUNT
$936.95
FM
Approved B Accepted By: e�; 2Z. &2t
City Engineer Northwest Asphalt, Inc. Au I Representative
Date: Date:
a It