HomeMy WebLinkAbout20070820 - VIII-C-3
VIII-C-3
MEMORANDUM
TO:
FROM:
DATE:
SUBJECT:
Honorable Mayor and City Councilmembers
Dave Osberg, City Administrator
August 16, 2007
Public Dock Installation Status
Joel Toso, from Polaris Group Engineering, the consulting engineering company assisting
the City with the public dock project will be in attendance at the City Council meeting on
Monday August 20,2007. Mike Noonan with Portable Barge, the company with the
contract to install the dock, ramp and pilings has also been invited to attend the meeting
on Monday night.
The piling material has been acquired by Portable Barge, and installation had been
scheduled for the week of August 19, 2007. The dock is currently stored on a barge at
Portable Barge's slip in Newport. Most of it has been assembled, looks good, and there
are no apparent flaws.
Until earlier this week, it appeared the dock and pilings could be installed next week.
However, Portable Barge has been working the last several weeks at the site of the
Highway #35W Bridge collapse, On Wednesday August 15,2007 Mr. Toso and Mr.
Noonan discussed the various projects Portable Barge is working. In addition to their
work at the Highway #35W Bridge collapse, Portable Barge has the Hastings dock
project and work for the City of St. Paul in the downtown river area. Portable Barge has
pulled off both of those projects as of Tuesday August 14,2007, and focused all of their
staffing and equipment resources at the Highway #35W Bridge collapse, The 35W
Bridge effort continues to expand its demand for resources and has asked for every barge
available from Portable Barge. The Highway #35W effort is expecting to complete the
recovery of the victims, and begin the debris removal stage, with no schedule established
yet, on when the demand for barges will decrease, and Portable Barge will be able to
return to their other projects in Hastings and St. Paul.
Several options will be addressed on Monday. As those are considered, recall that the
dock is currently stored at the Portable Barge slip in Newport; covered by their insurance,
Reasons to have the dock installed this year:
-Public Approval
-Check that the dock works well
Reasons to wait until next year:
-The 35W work will likely push the installation out of the main boating season
- The dock is currently stored out of the water, on a barge, and insured
Needless to say, neither option is especially attractive, Joel Toso has recommended that
we wait until early next spring for installation, Staff will attempt to gather further
information prior to the meeting on Monday August 20, 2007, Be assured, that both Joel
Toso and Mike Noonan have been very helpful and cooperative with this project, and
neither are thrilled with the idea of delaying the installation until next year. Yet, unless
additional information or options become available, prior to, or at the City Council
meeting on Monday August 20, 2007, Staff would recommend that action be taken
directing Staff to work with Mike Noonan and Portable Barge to prepare a letter of
understanding, or some type of agreement, addressing this situation, assuring timely and
effective installation of the dock, pilings and ramp early in the spring of 2008, and other
consideratio relating to insurance and contractual responsibilities.
David M. Osberg
City Administrato