VI-7
MEMO
To:
From:
Date:
Re:
Honorable Mayor and City Council
Tom Montgomery
August 29, 2007
Accept Quote - Downtown Quiet Zone 2nd S1. Watennain Crossing Stub
Quotes for the trunk watennain stub crossing 2nd Street at Bailly St. will be
opened the morning of September 4th. This watennain stub needs to be installed prior to
the Quiet Zone median improvements and will ultimately be connected to the new trunk
watennain planned for the Downtown area. The cost of the water main stub project will
be funded through the Water Fund. A memo listing the quotes received and
recommending acceptance of the low quote will be handed out to the Council prior to the
September 4th Council meeting.
MEMO
To:
From:
Date:
Re:
Honorable Mayor and City Council
Tom Montgomery
August 29, 2007
Accept Quote - Downtown Quiet Zone 2nd St. Watermain Crossing Stub
Council is requested to accept the low quote of $3 8,856.65 from Otto Excavating
for installing a 2nd Street trunk water main crossing stub in advance of the Quiet Zone
median improvements. This watermain stub will ultimately be connected to the new
trunk watermain planned for the Downtown area and will be funded through the Water
Fund. Below is a listing ofthe three quotes received:
CONTRACTOR
Otto Excavating
Gartzke Construction
Nova-Frost,Inc
QUOTE
$38,856.65
$42,381.00
$43,465.00
-