MEMO
To: Honorable Mayor and City Council
From: Nick Egger -City Engineer
Date: June 5, 2008
Re: Award Contract -Project 2008-2, Downtown Street & Watermain
Improvements
Bids were opened for the Downtown Street & Watermain Improvements on Thursday,
June 5, 2008. The low bid came in about 10% below the estimated construction cost.
Enclosed for Council approval is a resolution awarding the contract to the low bidder,
Pember Companies, Inc. in the amount of $1,265,740.85.
- .~
crrY of ~~srixss
CITY OF HASTINGS
DAKOTA COUNTY, MINNESOTA
Resolution No.
RESOLUTION RECEIVING BIDS AND AWARDING CONTRACT FOR PROJECT
2008-2, DOWNTOWN STREET & WATERMAIN IMPROVEMENTS
WHEREAS, pursuant to an advertisement for bids for Project 2008-2, the Downtown
Street & Watermain Improvements, bids were opened on June 5, 2008 and tabulated
according to law, and the following bids were received:
Bidder Bid
Pember Companies, Inc. $1,265,740.85
Ryan Contracting Co. $1,285,808.68
Northdale Construction $1,363,610.80
WHEREAS, Pember Companies, Inc. is the lowest responsible bidder
NOW, THEREFORE BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF HASTINGS AS FOLLOWS; that the Clerk and Mayor are hereby authorized and
directed to enter into a contract with Pember Companies, Inc. in the amount of
$1,265,740.85 for Project 2008-2, the Downtown Street & Watermain Improvements.
ADOPTED BY THE CITY COUNCIL OF HASTINGS, NIINNESOTA, THIS 17~
DAY OF JUNE, 2008.
Ayes:
Nays:
Paul J. Hicks, Mayor
ATTEST:
Melanie Mesko Lee, City Clerk (Seal)