HomeMy WebLinkAbout20080707 - VI-17VI-17 MEMO To: Honorable Mayor and City Council From: Tom Montgomery Date: July 1, 2008 Re: Change Order #5, Public Works Office Expansion Council is requested to approve the enclosed Change Order #5 for the Public Works office expansion construction. The total for the 9 change order items is $6,868 and incorporates a number of small items that were overlooked in the original bid package. The project budget includes the $1,343,000 original bid for building construction plus $67,150 for contingencies, for a total of $1,410,150. With Change Order #5, the contract amount has increased to $1,404,327; still within the project's budget. The office expansion has received a temporary certificate of occupancy, and Public Works is expected to move in the week of July 7, with Engineering moving from City Hall to the new Public Works office near the end of July, depending on the street and utility improvements construction activity. Site work on the exterior of the project is getting underway, with a large percentage of the work being completed by Public Works operators. Site work is expected to be substantially completed late this fall. .~ _ -~- ~. crrYoF-~s~ruvss N;~; ~``~ -:~-~ ~ Document G701'" - 2001 " ~£~ _ _ , ;.change Order... • ~ ~K: - `"'.,' ~ ~,~2bJ (nine and ad~ss): CHANGE ORDER NUMBER: 005 OWNER: . ` ~ _ j;T~estings Public Works.Expansion DATE: June 26, 2008 ARCHITECT: 1225 Progi~s~DXive Fastings,;A~11~,5033 :. _... _. CONTRACTOR: :; ;TfI.CONT~iACT;~,R (l~arilg:andaddress): ARCHITECT'S PRO.~CT NUMBER: 13725b.000 FIELD:_^ =;(gnstnu~ion'1~',`~suj~~iporatio CONTRACT DATE: September 17, 2007 _ _ 1:417Q ~3rdw.4ve>!, ~t%th " .. CONTRACT FOR: General Construction OTHER: ^ " ; : ~.: " CO~!ITRA4T•)!S ~ AS FOLLOWS: . „ , (/nc lade. -Yher'e apPlrca~il~xiiry rtrylisputed amount attributable to previously executed Constructron Change Directives) _-~ :•.:- 1 '~ ~;~[4s per Prop Re~-1Vo. 28 dated May 30, 2008, provide a motorized ' dhmper tflr the re~id~xd'i~t. Contractor's cost quotation dated June 4, 2008. Add: ~~o ~ $ 986.00 " ~:= ~ As per~GC i2etlues~t lYo.,l7 dated June 8, 2008, Provide additional flashing at ' ~;, ,;:sumtuntiels` Add $ 947.00 ~ „ ~ 3 tSs per~iC' In~t`No 18 dated June 9, 2008, provide additional floor preparation at ~ exrshng _dt~r s~rll:e~tnd extra ceramic tie work around the paper towel dispensers. Add $1,148.00 ;;~: 4 BAs per Gl. Request No. 19 dated June 9> 2008, provide emergency power off swrtch:fgi the boilers in the mezzanine mechanical room Add: $ 945.00 .: ~:` ;~: 5, . As per CiC`Request No '~ June 9, 2008, provide matching plastic laminate r '(w lieu. of whited at the c]~qy~ shelf. Add: $ 195.00 ,~~ ,~ 6 As per GC Request Ido 21. dated June 10, 2008, provide additional lighting ('1'-4) " .~- '; :.. ;with occupancy segspJr-~ t~[e existing Server Room No. 107. Add: $ 663.00 }` .. 7 .As per ~C t~equest No: ~,¢at~"d June 20, 2008, time and materials to modify m~:;,:,,:` ;jorsf-bracing`at three (3)'siiri tunnels. Add: s- $ 634.00 : . , ~$ AsR' GC G~o~~ ,dated June 25, 2008, furish, wire, and program the 1~94~, ,~ „ materials retqutreFL to and display the status of existing exhaust fan. Add: ~~~ $ 985.00 ' -.d. , ~ ~ ~ ~'9 As ~ itequest No. 24, dated Jnne 27, 2008, famish and install restmom srgns. ~ ~,... Add: $ 365.00 :: •.. ~U: > '. '• , ^ .. ~ Total Addition: 6,868.00 The~ri~a1,:,Contract Sum was ; 1,343,000.00 7~e ~t~.clange by previously audlorized Change Orders 5 54,459.00 x`e~~~ Sum-prior to this Change Order was ; $1,397 459.00 ,_`1~e Contiatt S'tii'tnivill be increased by this Change Order in the amount of ; 6,868.00 Ttte rieu~ C4p1~Smn including this Change Order will be $ $1,404,327.00 The Contract Trme will be unchanged by Zero (Q) days. The date of Substantal Completion as of the date of this Change Otder therefore is June 30, 2008 NOTE: This Change Order does not include changes in the Contract Sum, Contrail Time or Guaranteed Maximum Price which have been authorized by Construction Change Directive until the.cost and time have been agreed upon by both the Owner and - Contractor, in which case a Change Order is executed to supersede the Constructon Change Directive. AIA Document G707TM -2001. Copyright ®1979, 1967, 2000 and 2001 by The American liistitute of Arahicects. AO rights reserved. WARIMMQ: 71ds AIA° Document Is protected by US. Copyright Law and irt~rratbnal Trestles. UtrarRhorized reprodtatxlon ar distrlbutlon of this AIA° Docunertt, ar aoy ~ portion of it, may result M severe civil and criminal penaltles, and will be prosecuted to the maximum ezteM possible under the law. This document was produced by AIA software at 07:42:54 on 07/01/2008 under Order t+b.1000340371_1 which expires on 1/27/2009, and is not Sion resale. User Notes: (3757483237)