HomeMy WebLinkAboutVIII-09 Approve Change Order No. 1 for the Central Water Treatment Plant – Raw Watermain ProjectCity Council Memorandum
To: Mayor Fasbender & City Council Members
From: Ryan Stempski, P.E. – Public Works Director
Date: November 17, 2025
Item: Approve Change Order No. 1 for the Central Water Treatment Plant – Raw Watermain Project
COUNCIL ACTION REQUESTED
Council is requested to approve the attached change order for the Central Water Treatment Plant – Raw
Watermain Project.
BACKGROUND INFORMATION
The Change Order identifies the cost savings to the City to change construction methods from open cut to
directional drilling the raw watermain pipe for a portion along 7th Street W. This was done not only as a cost
savings but also to reduce impacts and conflicts along a portion of the corridor. The contract time was not
amended with this change order.
FINANCIAL IMPACT
The value of the work for Change Order No. 1 is a reduction in cost of $51,874.12.
Below is a table summarizing the Change Orders.
Central Water Treatment Plant – Raw Watermain Project Change Order Summary
Change
Order Date Item
Estimated
Value
1 11/17/2025 Change construction method from open cut to directional drilling for a
portion of 7th Street W
($51,874.12)
Net Total Increase/(Decrease) to date ($51,874.12)
Original Contract Value $3,160,083.00
Change Orders as Percentage of Original Contract Value to date 1.6%
STAFF RECOMMENDATION
Staff recommends approval of the attached change order.