HomeMy WebLinkAboutVIII-08 Approve Plans and Authorize Advertisement for Bids - 2025 Mill & Overlay City Council Memorandum To: Mayor Fasbender & City Council Members From: John Caven – Assistant City Engineer Date: February 10, 2025 Item: Approve Plans and Authorize Advertisement for Bids – 2025 Mill & Overlay Program Council Action Requested: The council is requested to adopt the enclosed resolution approving the 2025 Mill & Overlay Program and authorize advertisement for bid. Background Information: A mill and overlay is a street maintenance technique that extends street life by removing and replacing the top layer of asphalt. After the top layer is removed, a new layer of bituminous pavement is put back in its place. The process is ideal for streets with: Age: 20-25 years old Pavement Condition Index (PCI): 55-70 (on a 0-100 scale, with 100 being new pavement) Cross Section: Minimum 4” pavement thickness Surface Condition: Widening cracks, increasing potholes, rising maintenance costs Base Condition: Generally in good shape The project will mill and overlay 2.92 miles of streets, resurfacing the top 2” of pavement on the following roads: 4th Street: Dakota Summit Drive to General Sieben Drive 16th Street through 23rd Street: Pleasant Drive to Westview Drive Featherstone Road: West end to Pleasant Drive High Point Court: Northridge Court through Cul-de-sac Northridge Court: Northridge Drive through Cul-de-sac These streets, built between 1995 and 2005, have PCI ratings within or slightly below the target range. Their deterioration is primarily due to surface stripping and potholing, while the base remains in decent condition, making them strong candidates for mill and overlay. The project also includes Upgrading sidewalk pedestrian ramps with truncated domes for ADA compliance Spot replacement of curb and gutter, gate valves, and utility castings Providing traffic markings consistent with the existing layout. Construction will begin as early as May 5th and be wrapped up by no later than June 25th. The entire process should take approximately 4-6 weeks. Financial Impact: All streets are residential non-State Aid streets and have a budget of $1,000,000. The project estimate is generally within project budgets. Attachments: Project Map Photos of Present Condition VIII-08 CITY OF HASTINGS DAKOTA COUNTY, MINNESOTA RESOLUTION NO ________ RESOLUTION APPROVING PLANS AND AUTHORIZING ADVERTISEMENT FOR BIDS FOR 2025 MILL & OVERLAY IMPROVEMENTS WHEREAS, the City contracts for a mill and overlay project as part of its pavement maintenance and preservation plan; NOW, THEREFORE BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF HASTINGS AS FOLLOWS; that 1. Plans and specifications for the 2025 Mill & Overlay Program prepared by the Hastings City Engineer are hereby approved as presented, and; 2. The City Engineer shall prepare and cause to be inserted on the Quest Construction Data Network web site, and on the City of Hastings official web site an advertisement for bids for the construction of the approved 2025 Mill & Overlay Program in accordance with such approved plans and specifications. The advertisement shall be published for three weeks, shall specify the work to be done, shall state that bids will be opened at 10:00 AM, Thursday, March 20, 2025 using online bidding through QuestCDN.com, and that no bids will be considered unless accompanied by a bid bond for 5% of the amount of each bid. ADOPTED BY THE CITY COUNCIL OF HASTINGS, MINNESOTA, THIS 18TH DAY OF FEBRUARY, 2025. Ayes: Nays: Mary Fasbender, Mayor ATTEST: Kelly Murtaugh, City Clerk SEAL VIII-08 VIII-08 2025 Mill and Overlay Program Existing Condition 4th St – looking west from Hastings High School entrance 16th St – looking west from Westview Dr 17th St – looking west from Westview Dr 18th St – looking west from Westview Dr 19th St – looking west from Westview Dr 20th St – looking west from Westview Dr VIII-08 21st St – looking west from Westview Dr 22nd St – looking west from Westview Dr 23rd St – looking east from Pleasant Dr Featherstone Rd – looking west from Glenlou Way Northridge Ct – looking north from High Point Ct High Point Ct – looking east from Northridge Ct VIII-08