City Council Memorandum
To: Mayor Fasbender & City Councilmembers
From: City Administrator Dan Wietecha
Date: November 4, 2024
Item: PFAS Update
Council Action Requested:
Informational memo, no action requested at this time.
Background Information
Hastings has PFAS contamination in all six of our municipal wells (specifically PFOA in all six
wells and PFOS in two wells). We’ve also now found PFOA levels over the EPA’s limit in the
future Well No. 9 site. The City has completed a Feasibility Study to consider alternatives to
mitigate the PFAS. The study recommended construction of three decentralized water treatment
plants for PFAS and Nitrate removal.
The general plan is to build one WTP per year for three years. The current construction cost
estimate is $68.9M with expectation to trend higher. Without financial assistance, water rates
would need to double in three years and triple in five years. The City has been exploring and
pursuing multiple opportunities to offset this “budget buster” expense.
Key Updates
Siting Study: The Feasibility Study is a planning document, geared toward functionality and
cost effectiveness, not final sites. This summer Public Works followed up with a Siting Study to
identify several potential sites for WTPs 2 and 3. There was a strong preference to avoid
residential neighborhoods.
Potential sites were vetted against engineering criteria such as proximity to water and sewer
infrastructure, proximity to wells, adequately sized water mains, road access, and location within
pressure zones. Then they were modeled for feasibility and reviewed for cost estimates based on
land acquisition and length of watermains and sewer mains that would be needed.
This study was presented at the September 3 City Council meeting, with preferred sites on North
Frontage Road for WTP 2 and on General Sieben Drive for WTP 3. On September 16, City
X-E-01
Council met in a closed session pursuant to Minnesota Statutes 13D.05 subd 3(c) to develop
offers for purchase of real property.
Subsequently, we have hired Valbridge Property Advisors for appraisals of the two sites.
Additionally, SRF Consulting Group is recommended to conduct a lease analysis to help with
statutory requirements for relocating existing businesses at the North Frontage Road site.
State Capital Budget: The City submitted PFAS Treatment & Raw Water Lines for
consideration in the State’s 2024 Capital Budget due to the budget-busting expense, the fact that
the treatment is to remove contamination/pollution caused by others, and the suddenness of new
regulations preventing financial planning. Sen. Seeberger and Rep. Hudella indicated support
and introduced SF 3161 and HF 3115.
The legislative session ended May 20 without passage of a bonding bill. I expect we will renew
our State Capital Budget Request for next session. In October, we met with Senator Pappas,
Chair of the Senate Capital Investment Committee, to provide an update on our project and
funding needs. A new state application as well as new bills will be needed. This will be on the
agenda for the City Council’s Legislative Priorities Workshop on November 16.
Minnesota Veterans Home:
The Minnesota Veterans Home is presently served by a private well, which also has PFAS
exceeding the EPA limits. In discussions with leadership at the Veterans Home, we had the first
phase of our project include design of an interconnection of the Veterans Home water system to
the City’s water system, avoiding the need for the Veterans Home to construct and maintain a
treatment plant for its private water system.
Without state bonding to cover the first phase, the City cannot cover the cost of the interconnect.
The Veterans Home may now conducting a feasibility study to determine whether to construct
and maintain its own water treatment plant or to connect to the City water system. We offered
that we could assess the connection at an estimated cost of $1.7M. This does not need to be done
as part of the WTP 1 phase; it can relatively easily be picked up singly or in conjunction with
either of the other WTPs.
Congressionally Directed Spending / Community Project Funding: In April, we submitted
requests of Senator Klobuchar, Senator Smith, and Representative Craig for $10.3M (50%) of
the first phase of the project. This amount is higher than typically funded.
All three advanced our request to their respective Appropriations Committees; however, it was
not approved through the Senate Appropriations Committee. As it worked through “mark up” by
the Appropriations Committees, it is now proposed at a little over $1M. This is a first step and
not a final decision. Senator Smith’s office said that approval would not occur until November at
the earliest and potentially into 2025.
X-E-01
PPL/IUP: In 2023, the City submitted the project for the State’s Drinking Water Revolving
Fund Project Priority List (PPL). On May 1, 2024, we re-submitted to correct errors and to
recognize new EPA regulations of MCLs for PFAS, which will result in our ranking at or near
the top of the list. Additionally, we submitted the first two phases of the project for the Intended
Use Plan (IUP) in early June. Although the Drinking Water Revolving Fund is not our preferred
funding source, it has the possibility of a $3M Emerging Contaminants Grant for each phase. We
have been told that grant decisions will be in November.
Water Rates: With budget planning for 2025 (including workshops on June 3, June 17, and
September 3), we discussed potential water rate increases, phasing, and timing. During our
October 21 meeting, the City Council supported a two-step water rate increase in 2025, with a
10% increase effective January 1, 2025, and a second increase to be determined effective July 1,
2025. On an average residence using 15,000 gallons per quarter, the January increase would be
about $4 per quarter.
Additional increases are expected to coincide with construction of each of the three WTPs. In
total, rates would double in three years and triple in five years without financial assistance.
Communications staff sent a postcard to all residents/businesses around October 29 notifying
them of the pending increase. Other parts of the communications plan include utility billing
inserts, letter to largest volume water users, FAQs on the website (these will also help front desk
staff to answer questions and will also be printed as handouts for people without computer
access), KDWA interview, overview and Q&A with Chamber of Commerce Government Affairs
Round Table, newsletter, and social media.
3M Settlement: The 2018 Settlement Agreement provides grant money for drinking water
projects “in the East Metropolitan Area.” It is not limited to any specifically named cities or
townships and does not require a direction connection to one of the 3M disposal sites. Similarly,
Minnesota’s Conceptual Drinking Water Supply Plan does not require a direct connection to one
of the disposal sites. However, the State’s Co-Trustees (MPCA and DNR) have stated that a
direct connection should be required and has excluded Hastings from funding under the
Settlement Agreement.
Although we disagree with the Co-Trustees’ interpretation, we value our relationship with them
and have endeavored to not have this disagreement come between our mutual efforts. The
MPCA has been helpful in conducting Phase I and II environmental site assessments, requesting
3M to conduct additional investigation of its disposal site and hydraulic modeling in the Hastings
area, and has awarded a planning and design grant for Hastings to begin design engineering for
the treatment plants.
X-E-01
Additionally, the 2007 Consent Order does require a direct connection to one of the East Metro
disposal sites. This is extra important since the Co-Trustees have acknowledged that the
Settlement Funds will run out as they cover currently proposed East Metro projects, so they will
be transitioning to the Consent Order in the next couple years.
We believe the environmental studies have resulted in several lines of evidence of a connection
of Well #5 to the 3M Cottage Grove site, specifically: updated Minnesota Geological Survey
mapping of a fault in the bedrock, presence of HQ115/TFSI in Well #5, and additional water
composition and PFOA chemical analyses.
We met with the Co-Trustees and Attorney General’s Office in late July, and they agreed that
there is a connection between Well #5 and 3M. In October, they agreed that there is a connection
between Well #5 and the 3M Cottage Grove site and that the costs associated with Well #5 (to be
treated with the central WTP) would be eligible for funding under the 2018 Settlement
Agreement. We estimate the costs associated with Well #5 to be $14.5M, but that amount has not
been reviewed or approved by the Co-Trustees.
In the meantime, the environmental investigations will continue as planned by the MPCA to
determine connection and eligibility for the City’s other wells.
Central Water Treatment Plant: During our October 21 meeting, the City Council agreed to
flip the sequence of the construction schedule: proceed with the central WTP (WTP 2) in 2025
and delay the eastern WTP (WTP 1) until 2026.
Proceeding with the WTP that has significant outside funding has two major advantages. 1) It
would mean a smaller water rate increase for our residents and businesses. 2) It gives us
additional time to seek state bonding, grants, and/or direct connection to 3M Cottage Grove
before proceeding with the other WTPs.
We intend to move forward with Geotechnical Investigation and Topographic Survey to design
the new site location for the central WTP with the WSB team that conducted the work on eastern
WTP site already. WSB has been cost effective and efficient with the work due to their expertise,
understanding of scope, close coordination with the City, flexibility on direction, and
responsiveness to listen and meet the City’s needs. Continuing with the team that has developed
the water system modeling, WTP Siting Study, and treatment plant design specific to Hastings
eliminates re-work and a learning curve that would add more expense and time to the project.
This work is scheduled to be completed in the month of November in advance of the winter
season.
At present, we anticipate final design could be completed and ready to id by late spring / early
summer 2025.
X-E-01
Financial Impact:
Not applicable
Committee Discussion:
Not applicable
Attachments:
Not applicable