HomeMy WebLinkAboutVIII-08 Approve Change Order - Three Rivers Trail Project
City Council Memorandum
To: Mayor Fasbender & City Councilmembers
From: Chris Jenkins, Parks & Recreation Director
Date: October 21, 2024
Item: Approve Change Order
Council Action Requested:
Approve Change Order for Three Rivers Trail Reconstruction Project
Background Information:
The Three Rivers Trail segment connecting the Tuttle neighborhood to East
31st Street was recently awarded. During the design and engineering phase,
staff removed a few elements to ensure the projected project costs remained
within the budget allocation. After bids were received, and a pre-construction
walk of the project, staff propose to return 2 elements to the project, and to
provide funding for an unexpected and unknown element of the project.
• Flint Hills Resources Pipeline Crossing: although it was known that
this trail would cross FHR pipelines, it was not known until the project
pre-con meeting that a high-pressure propane line was very shallow
within the trail corridor. The pipeline is 2ft deep and at that shallow
depth requires extra precautions for equipment and trucks to cross.
• Spur Trail: a spur trail that connects this trail segment to the Three
Rivers Neighborhood was removed from the bid package, it is now
apparent that it should be returned to the project, and funding is
available. This is a major connection between the neighborhood and
the main trail.
• ADA Pedestrian Ramp: the current project includes replacement of
one ADA Ped Ramp on the west side of the intersection of East 31st
Street and Amelia Avenue. It is apparent the eastern ADA Ped Ramp
should also be replaced with this project, and the cost will remain
within budget.
Our contractor has provided a cost estimate of $37,448.25 to complete this
extra work.
VIII-08
Financial Impact: Project to remain within authorized budget.
Total budget for the project authorized in the 2024 budget: $393,000.
• Design & Engineering - $41,000
• Survey - $2,800
• Construction - $249,532.50
o Total cost prior to change order: $293,332.50
o Change order cost: $37,448.25
▪ Total project cost including change order: $330,780.75
Advisory Commission Discussion:
None
Council Committee Discussion:
None
Attachments:
▪ Change order cost estimate.
▪ Project images related to change order request.
VIII-08
Section Title
Line
Item
Item
Code Item Description UofM Quantity Unit Price Extension
BASE BID
1 2021.501 Mobilization (paver and milling) LS 1 $4,250.00 $4,250.00
2 2104.503 Remove Concrete Curb & Gutter LF 60 $17.50 $1,050.00
3 2104.504 Remove Concrete Pavement SY 15 $35.00 $525.00
4 2104.504 Remove Bituminous Roadway SY 85 $27.00 $2,295.00
5 2104.504 Remove Bituminous Walk SY 151 $5.00 $755.00
6 2104.503 Sawing Bituminous Pavement LF 96 $20.00 $1,920.00
7 2106.507 Excavation - Common CY 38 $20.00 $760.00
8 2211.507 Aggregate Base (CV) Class 5 CY 38 $47.50 $1,805.00
9 2301.504 Concrete Pavement 4" SY 34 $200.00 $6,800.00
10 2360.504 Type SP 12.5 Wearing Course Mixture (3;B) 3" thick SY 123 $18.75 $2,306.25
11 2360.504 Type SP 12.5 Wearing Course Mixture (3;C) 2" thick SY 85 $65.00 $5,525.00
12 2360.504
Type SP 12.5 Non Wearing Course Mixture (3;C) 2"
thick SY
13 2531.503 Concrete Curb and Gutter Design B618 LF 60 $85.00 $5,100.00
14 2531.618 Truncated Domes SF 40 $70.00 $2,800.00
15 2563.613 Traffic Control LS 1 $1,500.00 $1,500.00
16 2573.501 Stabilized Construction Exit LS
17 2573.502 Storm Drain Inlet Protection EA 1 $175.00 $175.00
18 2573.503 Sediment Control Log Type Wood Fiber LF
19 2575.505 Seeding ACRE 0.1 $1,000.00 $100.00
20 2575.508 Hydraulic Bonded Fiber Matrix LB 300 $2.00 $600.00
21 2575.508 Seed Mixture 25-131 LB 22 $6.00 $132.00
22 SP Construction Matting LS 1 $3,300.00 $3,300.00
Base Bid Total: $37,448.25