HomeMy WebLinkAboutX-E-02 Strategic Plan Quarterly Report
City Council Memorandum
To: Mayor Fasbender & City Councilmembers
From: City Administrator Dan Wietecha
Date: February 5, 2024
Item: Strategic Plan Quarterly Report
Council Action Requested:
Information only, non-action item.
Background Information:
In September 2023, the City Council adopted the 2024-2027 Strategic Plan. With the new plan, staff has
begun utilizing MS Project as the platform for tracking progress on the strategic initiatives.
We present an updated reporting format to be clear and readable. It indicates progress toward strategic
priorities and initiatives, upcoming initiatives, and any difficulties that we may have encountered. As in
the past, we will report progress to the City Council quarterly, as well as post publicly on the City
website.
We will schedule a City Council workshop (likely in April, ahead of the next budget cycle) for a more in-
depth discussion about the Strategic Plan.
Financial Impact:
Not applicable
Commission Discussion:
Administration Committee (Leifeld*, Haus, Pemble) reviewed the format of the report 1/29/2024
Attachments:
City of Hastings Strategic Plan Report – 4th Quarter 2023
X-E-02
CITY OF
HASTINGS
STRATEGIC
PLAN REPORT
4th Quarter 2023
X-E-02
Strategic Priority Desired Outcome
STRATEGIC PLAN SUMMARY 2024-2027
City of Hastings
2
Expanded revenue base
Responsible use of
debt
Spending aligned with
growth demands
Increase in revenues by
fund
Increase in revenue sources
Debt as percentage of
General Fund revenues
Operating budget
increase
CPI annual change
Tax base growth increase
10% non-tax revenue
increase (above growth)
2024-2027
Maintain compliance with City
debt policy
Debt financing plan developed
by 12/2024
Operating budget increases
limited to CPI + growth
adjustment annually
Key Outcome
Indicator Target Strategic Initiatives
Financial
Resilience
A financially sound
organization
Operational
Effectiveness
An organization that
delivers results
Responsive
Community
Development
Development that meets
present and future needs
Infrastructure
Sustainability
Infrastructure that
supports our community
Strategic
Communication
A transparent, responsive
government
Staff capacity to meet
service demands
% of authorized staffing
levels achieved
All departments meetauthorized staffing levels by
7/2024
Improved core service
delivery
# of core processes
improved% improvement in
processes
10% improvement in each
department's core process by12/2027
Improved workforce
capabilities
% of training
requirements met
# of credentials achieved
100% of employees meet
minimum training
requirements by 12/2024
Develop recruitment plans -
all departments
Process improvement
program
Develop organizational
training plan
1.
2.
3.
Alternative revenue analysis
Asset management funding
strategy (debt financing is
within this)
Budgeting system
evaluation
1.
2.
3.
Clarity regarding
housing supply needs
Successful development
of opportunity sites
Strategic Park
investments determined
Housing units available by
demographic segment
Housing demand by
demographic segment
Block 28 completion
Block 1 completion
Investment analysis
completed
Housing supply needs for all
demographic segments
determined by 12/2026
Block 28 completed by 12/2027
Block 1 completed by 12/2027
Park strategic investment
analysis completed by 6/2024
Housing needs analysis
Opportunity site
development strategy
Complete Vets Park and
Arena projects, including
economic investment
analysis
1.
2.
3.
Improved watertreatment capacity
Successful completion
of outsdie agency
projects
Expanded asset
management capability
Completed water system
improvements
Highway 61 rebuild
targets met
WWTP construction
targets met
Asset management plan
developed
Funding options
identified
Key water system
improvements completed by
12/2027
Highway 61 completed by
6/2028
WWTP completed by 12/2028
Comprehensive asset
management plan developed
and funding strategy proposed
by 2026
Develop asset management
plan
Implement water system
expansion plan
WWTP construction plan
Highway 61 construction
plan
1.
2.
3.
4.
Improved collaborative
relationships
Improved media
communication and
relationship
Enhanced community
engagement
Partner satisfaction
rating
# of one-on-one meetingswith local media
# of reporting inaccuracies
Improvements in
external responsiveness
Increases in inquiries via
technology
>90% of partners report
improved collaborative
relationship 2024-2027
Increase in one-on-one
communications with localmedia from 2024 to 2027
Community engagement via
expanded communications
options increases 10% 2024-
2027
Comprehensive
communication Plan
Collaboration improvement
plan
Community engagement
strategy
1.
2.
3.
City of Hastings Strategic Plan FY 2024-2027 | August 2023
1 1
•
•
•
••
•
•
••
•
••
•
•
•
•
•
•
•
•
•
••••
••
•
•
•
•
•
•
•
•
••
•
•
•
••
X-E-02
Reference Page 2 for the full plan summary.
Progress toward strategic priorities and initiatives will be reported quarterly.
Internal plan timelines will not require movement in all areas each quarter.
A timeline will be presented for the following quarter or years.
Legend:
Data Planning Deliverables
Understandingthe QuarterlyReport
Initiative Status:
Future Start On Track Delayed Complete
X-E-02
Q4 2023 Laying theFoundation
A new three-year Strategic Plan was
adopted by the City Council in
September of 2023. In Q4 2023,
staff laid the foundation for
executing the 2024-2027 plan.
Finalized goals/objectives.
identified action plans and
timelines to meet strategic
initiatives.
Began preparations for data
collection.
Already realized some action
item progress.
SUMMARY NARRATIVE
X-E-02
Strategic Priority: Financial
Resilience
Strategic Initiative: Alternative
Revenue Analysis
Identifying potential non-tax
revenue sources may allow the
city to minimize dependence on
the tax levy.
Researched and identified
non-tax revenue options
and assessed potential
revenue sources’ viability.
Calculated how much
revenue could be
generated from some of
the identified sources.
40% complete
Strategic Initiative: Asset
Management Funding Strategy
Developing a solid asset
management funding strategy
will allow the city to do long-
range planning for funding
capital equipment and capital
improvement projects.
Strategic Initiative: Budgeting
System Evaluation
Begins in 2025
In the process of reviewing
the City’s debt policy.
20% complete
X-E-02
Strategic Priority: Operational
Effectiveness
Strategic Initiative: Develop
Organizational Training Plan
Important staff training and
reporting have been
decentralized and lack
organizational consistency. The
objective is to develop a
centralized organizational
training plan and tracking for all
employees to ensure
consistency and compliance.
Identified critical training
targets for all employees.
Developed training plan
and annual training
schedule.
50% complete
Strategic Initiative: Develop
Recruitment Plans for all
Departments
Filling staff vacancies has
become more challenging and
hiring tends to be reactive.
Developing recruitment plans
that can be deployed as needs
arise through attrition or
expansion will enable the City
to be more effective in the
hiring process.
Strategic Initiative: Process
Improvement Program
Begins in 2025
Personnel baselines have
been identified for each
department.
25% complete
PLAN
X-E-02
D e v e l o p e d f u n d i n g s o u r c e s
a n d /o r a c q u i r e d p r o p e r t i e s
a t 4 t h a n d V e r m i l l i o n
S t r e e t s a n d n o r t h o f
A r t s p a c e d o w n t o w n .
1 5 % c o m p l e t e
S t r a t e g i c P r i o r i t y : R e s p o n s i v e
C o m m u n i t y D e v e l o p m e n t
S t r a t e g i c I n i t i a t i v e :
O p p o r t u n i t y S i t e D e v e l o p m e n t
S t r a t e g y
D e v e l o p i n g p l a n s f o r g r o w i n g
b u s i n e s s a l o n g H i g h w a y 6 1 a n d
d o w n t o w n i n c l u d e s p u r c h a s i n g
p r o p e r t i e s .
S t r a t e g i c I n i t i a t i v e : H o u s i n g
N e e d s A n a l y s i s
B e g i n s i n 2 0 2 6
S t r a t e g i c I n i t i a t i v e :
C o m p l e t e V e t s P a r k a n d A r e n a
p r o j e c t s , i n c l u d i n g e c o n o m i c
i n v e s t m e n t a n a l y s i s .
C i t y p a r k s a n d r e c r e a t i o n
a m e n i t i e s c a n d r i v e e c o n o m i c
g r o w t h i n c i t i e s . T w o p a r k s i n
H a s t i n g s o f f e r p o s s i b i l i t i e s f o r
e x p a n d e d e c o n o m i c i m p a c t .
C o m p l e t e d b i d d i n g
p r o c e s s f o r t h e V e t s P a r k
p l a n n i n g p r o j e c t .
C o m p l e t e d A r e n a
r e n o v a t i o n p l a n ,
s t a k e h o l d e r a n a l y s i s a n d
p r o j e c t c o s t e s t i m a t e s .
5 0 % c o m p l e t e
X-
E
-
0
2
Received $3 million in
design funding for the
treatment plants. Searches
for additional funding
continue.
25% complete
Strategic Priority: Infrastructure
Sustainability
Strategic Initiative:
Implement Water System
Expansion Plan
The city needs to design and
build three water treatment
plants to mitigate PFAS.
Strategic Initiative: Develop
Asset Management Plan
Begins in late 2024
Strategic Initiative:
Wastewater Treatment Plant
Construction Plan
Met Council Environmental
Services plans to move the
current Wastewater Treatment
Plant from downtown to the
border with Ravenna Township
in order to more effectively
serve the development of the
southeast metro.
Project design meetings
underway.
10% complete
Strategic Initiative: Highway 61
Construction Plan
MnDot and the City of Hastings
will reconstruct Highway 61
through Hastings, beginning in
2026 to accommodate growing
traffic and development.
Coordinated funding
requests continue. The
City recently was awarded
$2.7 million for the project.
A study has been ongoing
with stakeholders and will
conclude soon.
10% complete
X-E-02
Identified Data Collection
Needs
surveys on
communication tools
Drafted Comprehensive
Communication Plan
50% complete
Strategic Priority: Strategic
Communication
Strategic Initiative:
Comprehensive
Communication Plan
A transparent, responsive
government helps build trust
wtih our stakeholders and
allows us to meet their
preferences for
communications. A
comprehensive plan takes all
audiences and tools into
account and presents a
cohesive brand.
Strategic Initiative: Develop a
Collaboration Improvement
Plan
Begins in 2024
Strategic Initiative: Community
Engagement Strategy
Technology enhancements
allow organizations to engage
in two-way communications
with their diverse
audiences/customers. A
strategy to use the most
effective communications
platforms is essential to driving
community engagement.
Identified current tools and
technologies.
Developed plans for
enhancing web
accessibility and electronic
communications.
Conversions, upgrades
underway.
10% complete
CityHall
Hours:8:00a-m.to4:30p.m.Pnone:831-480-2350
Fan*31-437-7012AcOwtcngMnn.gov
Rivertown
Summer isontheway *seeinsiaeforHastingsFamiyAquaticsCenterfeesananours.ascneauleofsummerprogrammingatLeveePart,atniericleaguesanamore!PartyintnePortnappensJune6atLeveeParc.
6S1-S87-4867 Joinus:PoliceWeekOpenHouseTuesday.May16
5:C0to700p.m..HastingsPoliceDepartmentinfrontoftheHPOofficesonSiblevStreet.
X-E-02